Measurement Window
3-14 days of data logging
Service Detail
Field-data-based power quality audit to identify disturbance sources, evaluate operational impact, and design a measurable improvement roadmap.
Measurement Window
3-14 days of data logging
Parameters
THD, PF, unbalance, sag/swell, transients
Output
Executive report + action roadmap
MCB/MCCB or relays frequently trip without a clear cause.
PLC/server/device failures due to sag or transients.
Power factor or harmonics reduce system performance.
Does the audit require system shutdown?
No. Most measurements are performed during normal operation.
How long until the report is delivered?
Typically 3-7 working days after the logging period is completed.
Is implementation support available after the audit?
Yes. Our team can continue to the improvement implementation phase.